Site Meter

Having fun, while trying for the highest modelling standards that we can manage.
 

CHMRG BLOG

2007 Jul-Dec

 


7th August 07 - Three members met. Refitted (several times) the leg-retaining catch on end-board five - OK, but is easily dislodged if board 'jogged', so next session intend trying replacing with a small bolt. On board eight all the track dropper-wires connected to a small tagstrip - may need two further droppers at end; all track on this board now glued down. On board ten the bulk of the trackwork is now laid, and all glued down; need final aligning with boards nine and one still.

14th August 07 - Offline, Bill checked all switches on control panel, and replace two that failed. Then fitted the electronics 'chassis' to the back of the panel, sorted the 'common' wires and arranged in 'runs'. Then soldered all the common wires to switches controlling accessory decoder groups 0002, 0004, 0006 & 0022.

15th August 07 - Three members in session. End-board 10 tracks aligned with scenic board 9 and yard-board 1. A support-strip added on board 10 to support board 9 (which has no legs) during erection. Support-strip added under cantilever arm polted to board 10 which supports board 1, and an upstand at outer-end now allows a second M10 bolt fixing (into an embedded pronged-nut) to locate and support board 1. Then board 10 track wired to choc-bloc, and successfully tested.
Replaced the spring-catch leg-retainer on board 5 with a small bolt - now legs totally secure in transit/storage but still quickly deployed or stowed. But while further point-fettling was being done on board 5, pine-tree clips holding the leg-struts popped-out, and board nearly collapsed (with new loco on top!). Think problem is that repeated pushing in and out wears the clips and abrades the hole in the baseboard wood - therefore decided to abandon this part of QUAD, and think about alternatives.
A Hornby "DCC-ready" M7 was fitted with a TCS M4P-UK 'N' gauge chip; should have taken 30mins max., took two and a half hours! Involved shortening the wires on the TCS chip and those on the plug fitted on loco. So how "ready" is "ready", bearing in mind the TCS chip is physically smaller than the Hornby one. Works fine with MERG kit, though, once default direction corrected.

23rd August 07 - 'Offline' Bill wired more of the control panel - all Row one and a couple of Row two diode matrix connections done.

24th August 07 - Three members met, and were visited later for a short time by Ian, a prospective new adult member; he hopes to make the next session. Fraser and Rob continued working on the point-work on end-board 5 [B5]. Mark built the points originally as cross-overs for end-board 10 [B10], which only has up and down main lines, but on B5 the curvature of the up and down slow lines, outside the main lines, differ by a couple of inches, so we had to distort them somewhat to fit. It is that distortion that is causing the current trouble, although progess is being made - at least one more session will be needed before the point-work meets our current standards. Because of this our inaugural running session is now scheduled for mid-October.
Bill removed all the pine-tree-clip stuff from B5 and B10, after their dramatic failure last week. Then he fitted captive 6mm machine screws to B10 to hold the four leg-stays in the 'up' position using wing-nuts - this seems to work well. Bill then clamped a D25 connector to a short length of ribbon-cable, and fitted the assembly to B10.

29th August 07 - Five members met for a six-hour session. Fraser & Rob continued rebuilding the outer pointwork on end-board 5, then testing it with loco and short goods train, running successfully both ways though to points and crossover. Only one point, on the up-slow, remains to be re-built.
During our coffee-break we agreed in light of their work, supported by some back-to-back [B2B] measurements of locos done by Bill, that the Group would aim at a B2B measurement of 14.4 mm +/- 0.1 mm.
Our new member-elect, Ian, track-wired B9 to tag-strip; he then had to leave, so Brian completed glueing down the track on this board & he and Bill fitted the D25 connector, wired to the tag-strip - so B9 is now 'Phase One' complete.
The control panel wiring done by Bill 'off-line' was tested by Fraser, and it all worked except for 3 duff switches; unfortunately, though, because of a misunderstanding Bill had wired the 'point-normal' wires to the wrong side of each SPDT switch - redface time! But Bill will move these wired a.s.a.p., so we can test the panel with the storage sidings.

4th September 07 - Four members met for a five-hour session.Fraser and Rob had to completely re-build the down-slow point on B5, as well as some of the track around it.All now tested with locos and coach, so this board finally finished for Phase One running.
Brian unpinned the track on B9 that he glued last week, then fitted a D25 connector to B8, wired to the tag-strip. He and Fraser then fully tested the board with a DCC loco, controlled through the D25.
Bill puttered about as usual, but also fitted pronged-tees to B10 for the cantilever arm supporting B1. Then he did the QUAD leg retainer and captive M6 bolt for leg-brace (the other leg-brace on this board goes to B2 for extra stability). Finally he clipped the protruding long actuating wires on BI point motors.
Rob and Bill then sweated a bit fitting pronged-tees to B1 to speed the connection to B10, cutting away more of the B10 track-shielding to allow better access to the M10 bolt.

14th September 07 - Five members gathered for an eight-hour session (1 pm to 9 pm) so much was done. Pre-prepared leg-retainer bolts were screwed to B2 & B3, pronged-T-nuts fitted to B5/6 join and short leg-brace bolts put on B10. A platform to hold the MERG Programming Unit was built on B10. Leg retainers fitted to the middle storage siding boards B2 and B3. The alignment of B4 & B5 was checked and adjusted. B7 was wired, with extra droppers installed, and the D25 connector fitted. And some test-running was achieved.

18th September 07 - Red Letter Day - All ten baseboards were erected for the first time at the Mission. T-nuts added to scenic boards, and various adjustments and minor modifications made to several board-joins to assist with future assembling. Considerable progress was made with fitting the leg-retainers on the scenic boards, and with fitting captive bolts to secure leg-braces on all boards. Some work done fettling pointwork and track on the scenic sections. The ribbon-cable bus was begun, joining all the scenic boards, and some more trial running done over joints etc.

28th September 07 - Mainly a short (one and a bit hours) housekeeping session - in preparation for a major re-organisation of the Group's storeroom. However, a few minutes were spent finding, fixing and testing an electrical short on Board 7.

5th October 07 - Five members met, plus a visit from the ex-Chairman of late Brookside MRC, Mark, to see how we were getting on. Whole layout was erected again, with further work on QUAD (Quick Up And Down) project - apart from fitting / modifying the pronged T-nuts on the storage siding boards, this work is now complete. We estimate (after time-trials) that QUAD will have cut at least 30 minutes off the time to erect the full layout, and a similar time-saving on dismantling it. We are still experimenting with the exact order of erection/dismantling, but are fairly sure eventually it will take us no longer than 40 minutes to do either operation, ie. 1hr 20mins in total time-overhead for a running session. AND we are still looking at further ways to shave even more time off!
Other work done this session included re-hot-gluing two accessory decoder modules that had become detached from board 4 - if more hot-glued modules shake loose with handling, we will have to look to an alternative fixing method. The ribbon-cable bus carrying all the DCC commands and the traction power has been completed and tested - Adam managed to run an engine and six coaches right round the layout several times, although several minor electrical and track "faults" were found and noted for correction. Attention will soon be shifting to the scenic side of the layout.

12th October 07 - Four members present, plus a flying visit from the Chairman [pun intended!]. Adam beavered away on the Test-track, and has finished laying and glueing the outer, code 75, circuit, including soldering the rail-ends to solid brass screws at the baseboard joints. Rob and Brian tackled the uneven join between boards 4 and 5, and cracked the problem by letting in the copper-clad sleepers on board 4, thus bringing the rails to the same height as the rails on board 5 - a fiddly job which took over two hours, but the running across the join is now perfect. They then replaced one of the un-reliable leg-retaining ball-clips on one of the scenic boards with a bolt - working out the geometry of this exercised all our minds for a time, but we finally found a solution. Bill pottered about as secretaries do, sorting odd jobs and generally getting in the way, although he did make the tea.

19th October 07 - Four members present, although the Chairman only managed an hour because he was expecting an important equipment delivery at home. However, he and Ian started an intensive hunt for the short on B1 - which hunt Ian continued for the rest of the afternoon, aided as required by Bill and Adam. We ended with all the track-feeds and one frog-feed from the point motor switches disconnected, and the fault not showing. Next time we begin re-connecting the feeds until we find which one is causing the problem.
What this has shown is the difficulty in locating a fault in the wiring on a complex DCC board (a storage-siding fan in this case) when all the track feeds are effectively interconnected.
Adam and Bill continued with the test-track, and have started wiring the feeds, including plug & socket connections across the baseboard joints.

26th October 07 - Four members present. Fraser and Ian sorted out the short on B4 - and also replaced a point in the storage siding fan - Ian driving to SMTF shop at Brookside to get the replacement. Then tested board, and corrected three 'dead spots' on the track. Meanwhile Brian successfully fettled the cross-board track joints on the test-track, and Bill wired-up the D25 connectors for carrying the currents round the boards - the same pin-outs as on Attam Bank being used, which allows for the future incorporation of DCC controlled point-work and signals etc.

27th October 07 - Four members went to the Hazel Grove MR show this afternoon. We paid particular attention to the fascia / presentation of the layouts, and the nature and finish of the scenery on display - because we are just at the stage of starting our scenery. During the tea-break we had a good discussion, and decided we needed to have a re-think on the amount of "static interest" the layout would have - ie. something to hold the viewer's attention when no train is visible. It was noticeable that layouts such as Ecclesford Junction, which had plenty of interesting scenic set-pieces, held viewers attention much longer than some of the layouts depending on train movements to provide the interest. Of course all our wallets left the show considerably lighter than when they arrived!

2nd November 07 - All the ten boards were erected by two people (Fraser and Ian) in one hour - which was pretty good going! Three other people attended, but for various reasons weren't available till 2.0pm. One storage siding board (B4) was then taken down, and a frustrating three hours spent tracking down an elusive electrical fault - finally nailed by Rob and Ian about 5pm - it was a whisker of copper across a gapped copper-clad sleeper on the short entrance track from the down main. As the Chairman said, it's a learning curve!
In the meantime the Chairman had been correcting the silly wiring mistakes made on the control panel by Bill (still red-faced), and this was then 'hooked' into circuit on Attam Bank, where Adam, Ian and Rob were enjoying running trains round and round on both the up and down lines simultaneously. As the control panel was connected we all jumped when a number of points changed simultaneously - under DCC of course, when the panel 'fires up' it checks all the point positions and by default moves them all to the 'normal' position - the clicking was all those points we had reversed by hand being restored to normal. Preliminary testing indicates the control panel is behaving as designed.
Bill kept his head down, doing some wiring on the Test Track and also stencilling letters on the board sides to help get them in the right order when clipping them together. Both Ian and he took detail photos of the scenic section, and everyone discussed the scenic development of the layout. Overall a 'bitty' session, but at least we have finally got some trains running!

9th November 07 - Four members present - testing continued on the layout, and two points found to be faulty in storage sidings. One was replaced with spare, the other awaits purchase of replacement. On the test-track the inner, code 100, circuit was laid on Board A, plus the programming road and start of siding..

14th November 07 - Long bench in alcove removed with aid of our friends from Cheshire Fencing, whose yard is just behind the Institute. This means that on Friday we will be able to move the filing and steel cabinets into the alcove, making more room for us to erect the layout in the main hall.

16th November 07 - Four members met at 10.30 am, with Rob joining us from the airport at 1.00 pm - Adam unfortunately was trapped in the South, ironically by a cancelled train! The storeroom was cleared, and the racking moved to its new position on a sidewall - this all took a couple of hours, as the rack had to be partly dismantled to get it out of the restricted end of the room. At the same time the steel cabinet and two filing cabinets were emptied, and moved to new positions in the alcove. The library was returned to the 4-drawer file-cabinet, but time did not permit a full index today. However the contents of the steel cabinet were "inventoried" as they were returned. The 2-drawer file-cabinet now houses the shop stock, for sale at open-days etc.
We stopped at 2.0pm and had lunch, during which we held a short AGM. Then work began again, and we found that putting the layout boards back into the rack was now a "doddle" - we are kicking ourselves for not re-organising sooner! Some inventorying of the storeroom was done as we re-packed it - the sense of space is great. Still some detail work to complete, mainly getting things hung on wall to free floor space, but a great improvement already. Overall a very successful day.

23rd November 07 - Four members met, joined for a short time by former member Derek, who dropped in to see how we were getting on. Erected whole layout in just over an hour, but time spent sorting small jobs as we went - for example flattening the sharp track-pin ends that had penetrated the ply roadbed on board 4, on which one member snagged a finger. We also realised we had failed to cut isolator rail breaks in the cross-over on board 6 - this was done, and necessary additional 'invisible' track-feeds made by Fraser.
Further running tests using a train of bogie container wagons identified a track fault at the junction of boards 4 and 5; the baseboard surfaces are not vertically aligned which exacerbated the problem of moving from copper-clad sleepers to Peco code 75 track. This misalignment caused certain vehicles to de-rail on the three-way point where the up main enters the storage sidings - further examination revealed a slight but significant dog-leg where the soldered track met the toe of the point. Re-aligning these tracks is top priority for our next session.
Also decided next time to bring and run long passenger and goods trains, as just circling a loco with a couple of wagons could well not find all the track problems - perfect running is our goal, and we are prepared to spend quite a lot of time achieving it.

30th November 07 - All members attending Warley Show - Fraser will be demonstrating his DCC point actuator on the Bournemouth Model Railway Centre, Rob will be helping on the Castle Hill layout and the rest of us will be gadding about spending money and absorbing ideas that might transfer to Attam Bank.

7th December 07 - Bill and Fraser arrived at 13.30hrs, with the others trickling in over the next couple of hours. Nick, Adam's friend, came along this week, he gave Brian a hand with correcting the out-of-level joint between boards 4 & 5. Fraser mainly concentrated on the pointwork on board 7, in preparation for installing his new point actuators (which he demonstrated at Warley). Bill and Adam finished the inventory, after Bill had cured the "dropping leg-stay" problem on board 5. Ian dropped in for tea (Yorkshire Tea now, at his request - actually the year-old Tesco "economy" bags had seen better days!) . We had a discussion on the scenery plans, and agreed that while rolling-stock would mostly remain the property of individuals, some "scene-setting" trains (eg. one carrying tanks for the 1944 presentation) would be Group property. We agreed that all other scenic items, including removable ones, would be also be Group property. So, some progress, but much remains to do.

14th December 07 - Five members came, although Ian had to leave after 45 minutes - but before he went we discussed his proposal to add a high-level scenic baseboard above the tracks on end-board 5, with the scenery on board 6 modified to merge with the new board. The idea is to give more to hold a viewer's attention during the (hopefully brief) times no trains are moving on the scenic track section - agreed in principle, pending Ian's more detailed plans. We also discussed Bill's proposal that cross-overs would be needed between the up and down siding-fans in the storage sidings to facilitate "out-and-back" workings. It was decided to wait until we could run multiple trains in sequence to see how necessary this was.
Rob continued Brian's work on correcting the vertical misalignment at the junction of boards 4 & 5; this successfully completed this week, and trains consisting of various wheel-base plus bogie vehicles ran smoothly through; a variety of commercial wheelsets were included, all of which where OK.
Fraser continued his work on preparing the pointwork on board 7 ready for fitting his DCC-operated point actuators, and Adam built a test linkage to connect the main/slow points with the catch-point on the slow lines, so they could be operated by one actuator; this was proved to work. Adam & Bill also designed a mechanism/tool to adjust the back-to-back on commercial wheelsets.
Bill did some more re-organisation and sorting in the store-room, and replaced the old hand-written point labels on board 4 with more professional looking printed ones, sealing them to help keep them clean. He also labelled the filing cabinet drawers and converted some of the 10mm bolts used to connect the baseboards to allow a power screwdriver to be used to wind them into the pronged T-nuts.



    | Home | Current BLOG | 2007 Feb-Jun |

Powered by Recipero Working together with BT